Sub Navigation for Current Section

Update

Main Page Content

CPO Barge - Zurex POIC Lahad Datu
CPO Barge - Zurex POIC Lahad Datu
CPO Barge - Zurex POIC Lahad Datu
CPO Barge - Zurex POIC Lahad Datu
Loading of PFAD
Loading of PFAD
Loading of PFAD
Loading of PFAD
Loading of PFAD
Loading of PFAD
Loading of PFAD
Loading of PFAD
Director Dave Long at the POIC Interchange (Zurex's Pipes - Brown & Orange)
Director Dave Long at the POIC Interchange (Zurex's Pipes - Brown & Orange)
. Pipeline Section to Port Interchange
Pipeline Section to Port Interchange
 
Pipeline Section to Tank Farm
Pipeline Section to Tank
Farm
Pipeline to and from the POIC Jetty
Pipelines & Refinery -
Brown Crude & Orange Refiner Palm Oil
Pipeline to and from the POIC Jetty
Pipeline to and from the
POIC Jetty
Pipeline to and from the POIC Jetty
Pipeline to and from the
POIC Jetty
Pipeline to and from the POIC Jetty
Pipeline to and from the
POIC Jetty
Pipeline to and from the POIC Jetty
Pipeline to and from the
POIC Jetty
Pipeline to and from the POIC Jetty
Pipeline to and from the
POIC Jetty
Pipe Rack to Jetty
Pipe Rack to Jetty
 
 
CPO Being Discharged
CPO Being Discharged
Day Shift Management and Operators
Day Shift Management and Operators
Day Shift Team
Day Shift Team
Zurex front at night
Zurex front at night
CPO sampling
CPO sampling
Products transformation
Products transformation
Colour testing
Colour testing
Sample weighing
Sample weighing
Hotwell system
Hotwell system
RBD processing
RBD processing
Final RBDPO filtration
Final RBDPO filtration
High pressure boiler
High pressure boiler
High pressure boiler
High pressure boiler
RBDPO visual check
RBDPO visual check
Effluent treatment plant
Effluent treatment plant
CPO / RBD PO Loading / unloading bay
CPO / RBD PO Loading bay
Tanker on weigh bridge
Tanker on weigh bridge
Tanker seals being inspected
Tanker seals being inspected
CPO being unloaded
CPO being unloaded
CPO samples being tested
CPO samples being tested
CPO being discharged
CPO being discharged
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Boiler Area
Boiler Area
Refinery & Cooling Towers
Refinery & Cooling Towers
Refinery Tower
Refinery Tower
Zurex Refinery - First Light
Zurex Refinery - First Light
POIC Port Pipelines
POIC Port Pipelines
Processing Area
Processing Area
Receiving area
Receiving area
Boiler
Boiler
Cooler
Cooler
Front view
Front view
Internals from the front
Internals from the front
Internals from the back
Internals from the back
Picture Physical Refinery Plant: Steel Structure Erection
Physical Refinery Plant: Steel Structure Erection
Picture Pipeline connection between soft water tank and softener
Pipeline connection between soft water tank and softener
Picture Deareator Inlet and Outlet pipeline
Deareator Inlet and Outlet pipeline
Picture Oiltek equipment deliverey
Oiltek equipment delivery
Picture Pipeline connection to Physical Refinery Plant
Pipeline connection to Physical Refinery Plant
Picture 1000MT CPO Tank 
Inlet Pipeline
1000MT CPO Tank Inlet Pipeline
Picture Administration Building: Roof Truss
Administration Building: Roof Truss
Picture Administration Building
Administration Building
Picture Boiler House
Boiler House
Picture Boiler Installation
Boiler Installation
Picture Storage Tanks & Pipe Racks
Storage Tanks & Pipe Racks
Picture Administration Building - Slap in Progress
Administration Building - Slap in Progress
Picture Wight Bridge 2 - Cantilever Wall Complete
Wight Bridge 2 - Cantilever Wall Complete
Picture TNB Sub Station
TNB Sub Station
Picture Oil Pit - 80% Complete
Oil Pit - 80% Complete
Picture May 2010
May 2010
Picture May 2010
May 2010
Picture May 2010
May 2010
Picture Sabah Chief Minister officiating at a joint ground breaking ceremony organized by the POIC
Sabah Chief Minister officiating at a joint ground breaking ceremony organized by the POIC
Picture (April) TANK FARM PROGRESS
TANK FARM PROGRESS
Picture (April) Tank T201- Top Roof Setting in Preparation
Tank T201- Top Roof Setting in Preparation
Picture (April) High Pressure Boiler - Footing in Progress
High Pressure Boiler - Footing in Progress
Picture (April) TNB Sub Station- Super Structure in Progress
TNB Sub Station- Super Structure in Progress
Picture (April) Received & Despatch Area - Oil-Pit footing
Received & Despatch Area - Oil-Pit footing
Transfer Pumps
Transfer Pumps
Picture (April) Tank Farm
(April) Tank Farm
Picture (April) Tank Farm
(April) Tank Farm
Picture (April)-Tank 204 - Top Roof C-Channel in Progress
(April)-Tank 204 - Top Roof C-Channel in Progress
Picture (April) Tank T203 Heating Coil in Progress
(April) Tank T203 Heating Coil in Progress
Picture (April)-Boiler House- Column Concrete Casting in Progress
(April) Boiler House- Column Concrete Casting in Progress
Picture (April) Physical Refinery Plant- Deodorizer Footing Complete
Physical Refinery Plant- Deodorizer Footing Complete
Feb 2010 - Tank Farm - Tank Shell Plate First Layer View
ZUREX CORPORATION SDN BHD - PHYSICAL REFINERY PLANT (March 31, 2010)
Tank T203- Top Roof Setting in Preparation
Tank T203- Top Roof Setting in Preparation
Feb 2010 - Tank Farm - Tank Shell Plate First Layer View
Feb 2010 - Tank Farm - Tank Shell Plate First Layer View
Feb 2010 - Tank Farm - Tank Shell Plate First Layer View
Feb 2010 - Tank Farm - Tank Shell Plate First Layer View
Feb 2010 - Pump House - Rebar and Stump Complete
Feb 2010 - Pump House - Rebar and Stump Complete
Picture Mid-February 2010: Physical Refinery Plant - Ground Beam Rebar work complete
Picture Mid-February 2010: Physical Refinery Plant - Ground Beam Rebar work complete
Reinforcement Bar inside Form Work (600mm x 300mm)
Reinforcement Bar inside Form Work (600mm x 300mm)
Cross Over Pipe
Cross Over Pipe
Fabrication  of Deaerator
Fabrication of Deaerator
Excavator Start to Excavate first row of Refinery Plant
Excavator Start to Excavate first row of Refinery Plant
Fabrication of Package Boiler
Fabrication of Package Boiler
Fabrication of Gantry Structure
Fabrication of Gantry Structure
Secondary Clarifier of Waste Water Treatment Plant
Secondary Clarifier of Waste Water Treatment Plant
Physical Refinery Plant - Form Work & Lean Concrete Work for Each Section
Physical Refinery Plant - Form Work & Lean Concrete Work for Each Section
Tank 250MT concreting, total volume of concrete used is 21m³
Tank 250MT concreting, total volume of concrete used is 21m³
T401 & T402 Tank Foundation Completed
T401 & T402 Tank Foundation Completed
Tank T204 Centre Reinforcement Bar Work
Tank T204 Centre Reinforcement Bar Work
Tank Farm Overall View
Tank Farm Overall View
Cornerstone laying ceremony
Cornerstone laying ceremony