CPO Barge - Zurex POIC Lahad Datu
CPO Barge - Zurex POIC Lahad Datu
Loading of PFAD
Loading of PFAD
Loading of PFAD
Loading of PFAD
Director Dave Long at the POIC Interchange (Zurex's Pipes - Brown & Orange)
Pipeline Section to Port Interchange
Pipeline Section to Tank
Farm
Pipelines & Refinery -
Brown Crude & Orange Refiner Palm Oil
Pipeline to and from the
POIC Jetty
Pipeline to and from the
POIC Jetty
Pipeline to and from the
POIC Jetty
Pipeline to and from the
POIC Jetty
Pipeline to and from the
POIC Jetty
Pipe Rack to Jetty
CPO Being Discharged
Day Shift Management and Operators
Day Shift Team
Zurex front at night
CPO sampling
Products transformation
Colour testing
Sample weighing
Hotwell system
RBD processing
Final RBDPO filtration
High pressure boiler
High pressure boiler
RBDPO visual check
Effluent treatment plant
CPO / RBD PO Loading bay
Tanker on weigh bridge
Tanker seals being inspected
CPO being unloaded
CPO samples being tested
CPO being discharged
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Late December update
Boiler Area
Refinery & Cooling Towers
Refinery Tower
Zurex Refinery - First Light
POIC Port Pipelines
Processing Area
Receiving area
Boiler
Cooler
Front view
Internals from the front
Internals from the back
Physical Refinery Plant: Steel Structure Erection
Pipeline connection between soft water tank and softener
Deareator Inlet and Outlet pipeline
Oiltek equipment delivery
Pipeline connection to Physical Refinery Plant
1000MT CPO Tank Inlet Pipeline
Administration Building: Roof Truss
Administration Building
Boiler House
Boiler Installation
Storage Tanks & Pipe Racks
Administration Building - Slap in Progress
Wight Bridge 2 - Cantilever Wall Complete
TNB Sub Station
Oil Pit - 80% Complete
May 2010
May 2010
May 2010
Sabah Chief Minister officiating at a joint ground breaking ceremony organized by the POIC
TANK FARM PROGRESS
Tank T201- Top Roof Setting in Preparation
High Pressure Boiler - Footing in Progress
TNB Sub Station- Super Structure in Progress
Received & Despatch Area - Oil-Pit footing
Transfer Pumps
(April) Tank Farm
(April) Tank Farm
(April)-Tank 204 - Top Roof C-Channel in Progress
(April) Tank T203 Heating Coil in Progress
(April) Boiler House- Column Concrete Casting in Progress
Physical Refinery Plant- Deodorizer Footing Complete
ZUREX CORPORATION SDN BHD - PHYSICAL REFINERY PLANT (March 31, 2010)
Tank T203- Top Roof Setting in Preparation
Feb 2010 - Tank Farm - Tank Shell Plate First Layer View
Feb 2010 - Tank Farm - Tank Shell Plate First Layer View
Feb 2010 - Pump House - Rebar and Stump Complete
Picture Mid-February 2010: Physical Refinery Plant - Ground Beam Rebar work complete
Reinforcement Bar inside Form Work (600mm x 300mm)
Cross Over Pipe
Fabrication of Deaerator
Excavator Start to Excavate first row of Refinery Plant
Fabrication of Package Boiler
Fabrication of Gantry Structure
Secondary Clarifier of Waste Water Treatment Plant
Physical Refinery Plant - Form Work & Lean Concrete Work for Each Section
Tank 250MT concreting, total volume of concrete used is 21m³
T401 & T402 Tank Foundation Completed
Tank T204 Centre Reinforcement Bar Work
Tank Farm Overall View
Cornerstone laying ceremony